Project Details
Fixture installation, Road Line marking, Signage installation, Line marking removal
BuildCorp engaged us to supply and install a temporary raised pedestrian crossing and traffic islands at their Maroubra project. This project was time sensitive as it was part of a school project and it had to be delivered in the school holiday break.
The project took us 4 days to complete. We supplied and installed all of the new traffic signage and did all of the line marking to ensure that the new temporary fixture was as safe as possible while the local residents became familiar with it. On the first day of school the new pedestrian crossing was open and BuildCorp could continue with their building works as planned.